You Can't Assume Anything When Drafting A Proposal

The best rule to follow when drafting a proposal is to check every requirement in the solicitation, and then have your work doublechecked by someone else (or another team) to ensure that all required items are included. Don’t make assumptions about what the agency wants—ask in writing. If you fail to include required items, your proposal may be disqualified or scored lower than you expect. In Armstrong Elevator Co., B-422123, Dec. 28, 2023, the protester, Armstrong, (who was the low offeror) failed to write an adequate proposal that included all required information.


The Department of Veterans Affairs (“VA”) issued a solicitation for the replacement of cart transport elevators in a hospital building in Houston, TX. The award was to be made on a best-value tradeoff with two factors—past performance (significantly more important) and price (less important. The solicitation required the following


• Detailed summary of three recent and substantially complete contracts for elevator replacement work in an occupied hospital environment

• The solicitation identified nine categories of information that the detailed summary should discuss, including

o Project performance period (with initial and actual performance dates, schedule impacts and efficiencies);

o The names of any subcontractors used, their responsibilities and percentage of work performed; and

o A narrative that demonstrated experience with elevator installations in an environment similar to the Houston VA Medical Center (including details on complexity, magnitude, challenges and degree of success)


The solicitation stated that relative risks would be assessed, and likelihood of success as well. Finally, the solicitation stated that “Offerors are responsible for including sufficient details, in a concise manner, to permit complete and accurate evaluation of each proposal.


The evaluation results of the two highest offers was:

Armstrong Elevated

Relevancy Relevant Very Relevant

Confidence Satisfactory Substantial Confidence

Confidence

Overall Risk Low Risk Low Risk

Price $1,922,000 $1,948,710


In the evaluation, the VA assessed a weakness for each of Armstrong’s past performance items because the company did not provide all the required information. For each project, Armstrong’s proposal failed to address use of subcontractors (explaining during the protest that there were no subcontractors—but never stating that in its proposal), challenges encountered during performance and steps taken to overcome them, and initial and actual dates of performance. Armstrong did not clearly identify its past performance as having been in an active hospital environment, as required by the solicitation.


The Government Accountability Office (“GAO”) noted that it is the offeror’s responsibility to submit an adequately written proposal, including adequate information on past performance. Armstrong’s position was that the VA should have “assumed” that no subcontractors were used if no information concerning subcontractors was provided in its proposal, and that the projects were completed on time if only one set of dates was submitted for each project. GAO rejected Armstrong’s reasoning, noting Armstrong’s responsibility (as stated in the solicitation) to include such specific information in its proposal.

Takeaway: The offeror writes the proposal and must always comply with the solicitation requirements. Completeness is very important.


• When asked to provide information on subcontractors for a project, you might say “there were no subcontractors” or you should provide the detail on the subcontractors for the project.

• Always include detailed information concerning a solicitation’s request for all relevant (similar) past performance. Use the solicitation as a guide—make your proposal convincing.

• Respond with details to everything requested in the solicitation.


Takeaway. Never assume anything when writing a proposal. Scout the solicitation and fully comply.


For other helpful suggestions on government contracting, visit:

Richard D. Lieberman’s FAR Consulting & Training at https://www.richarddlieberman.com/, and Mistakes in Government Contracting at https://richarddlieberman.wixsite.com/mistakes.

4 views0 comments

Recent Posts

See All

Asserting Duress in Signing a Modification

Sand Point Services, LLC brought two claims before the Armed Services Board of Contract Appeals, both involving modifications.  Sand Point Servs., LLC, ASBCA Nos. 61819, 61820, January 4, 2024.  The f

Requirements Contracts: Words of Exclusivity

The Federal Circuit recently clarified that an agency’s contract may still contain requisite language to make it a requirements contract, even if the contract does not include the required Federal Acq

The website of Richard Donald Lieberman, a government contracts consultant and retired attorney who is the author of both "The 100 Worst Mistakes in Government Contracting" (with Jason Morgan) and "The 100 Worst Government Mistakes in Government Contracting." Richard Lieberman concentrates on Federal Acquisition Regulation (FAR) consulting and training, including  commercial item contracting (FAR Part 12), compliance with proposal requirements (FAR Part 15 negotiated procurement), sealed bidding (FAR Part 14), compliance with solicitation requirements, contract administration (FAR Part 42), contract modifications and changes (FAR Part 43), subcontracting and flowdown requirements (FAR Part 44), government property (FAR Part 45), quality assurance (FAR Part 46), obtaining invoiced payments owed to contractors,  and other compliance with the FAR. Mr.Lieberman is also involved in numerous community service activities.  See LinkedIn profile at https://www.linkedin.com/in/richard-d-lieberman-3a25257a/.This website and blog are for educational and information purposes only.  Nothing posted on this website constitutes legal advice, which can only be obtained from a qualified attorney. Website Owner/Consultant does not engage in the practice of law and will not provide legal advice or legal services based on competence and standing in the law. Legal filings and other aspects of a legal practice must be performed by an appropriate attorney. Using this website does not establish an attorney-client relationship. Although the author strives to present accurate information, the information provided on this site is not guaranteed to be complete, correct or up-to-date.  The views expressed on this blog are solely those of the author. FAR Consulting & Training, Bethesda, Maryland, Tel. 202-520-5780, rliebermanconsultant@gmail.com