top of page
  • Writer's pictureR.D. Lieberman,Consultant

Termination for Convenience Settlement Must Be Based on Cost, not Contract Line Items


The Armed Services Board of Contract Appeals (“ASBCA”) recently explained that a settlement of a termination for convenience must be based on the costs incurred by the contractor, not on either contract line item number (“CLIN”) prices or some type of jury verdict (because of the contractor’s inability to documents its costs). Atlas Sahil Const. Co., ASBCA No. 58951, Nov. 9, 2017.

The Army awarded Atlas a design-build, firm-fixed-price construction contract for expansion of a forward base in Afghanistan that supported U.S. forces. Eighteen months later, the contract was terminated for convenience pursuant to FAR 52.249-2 Alt I, because the base was going to be closed and there was no longer a need to expand it.

Atlas submitted a termination settlement proposal of $4.0 million, which the contracting officer rejected, concluding that “no settlement amount can be reached.” Atlas then submitted a claim for $4.2 million, including its settlement expenses. The settlement and claim were based on two methods of recovery: (1) the CLIN pricing in the contract, which Atlas asserted provided “the most reliable method for determining fair compensation; and (2) where CLIN pricing was not applicable, a “jury verdict” (i.e. an estimated amount where specific proof of cost was lacking) because Atlas was unable to present the determination of its costs.

The Board rejected both bases for the settlement amount, noting that CLIN prices are based on price, whereas termination settlements are based on cost—the cost of the work done and preparations made for the terminated portions of the contract. FAR 49.201(a), Additional Principles for Fixed-Price Contracts Terminated for Convenience. The CLIN prices do not reflect the contractor’s actual costs.

The Board also rejected the request for a jury verdict as unwarranted. A jury verdict is only used where a contractor has demonstrated a justifiable inability to substantiate the amount of its injury by direct and specific proof, citing Grumman Aero. Corp v. Wynne, 487 F. 3d 1350, 1358 (Fed. Cir. 2007). Here, Atlas asserted that it had a conflict with its subcontractor Sambros, which led to the subcontractor’s denying Atlas access to its records. But Sambros never testified regarding the dispute, the location of the records or their present condition. Further, Atlas’s claim ignored FAR 31.201-2(d) which requires a contractor to be responsible for accounting for costs and maintaining records and supporting documentation adequate to demonstrate its costs and comply with cost principles. The Board regarded the evidence in the record as sufficient to reach a decision without use of a jury verdict.

The Board then summarized each category of cost, plus profit (which it allowed at 5 percent, not the 25 percent claimed by Atlas, because of the difficulty of the actual work performed per FAR 49.202(b)(1)), and concluded with settlement amount of $1.5 million to Atlas.

The Takeaway: A contractor will not be permitted to base a convenience termination settlement on CLIN prices. It must use costs incurred. Nor will a contractor be allowed to receive a jury verdict, unless there is a justifiable inability to document its costs—and such an inability flies in the face of the FAR requirement that makes a contractor responsible for adequate documentation of its costs.

For other helpful suggestions on government contracting, visit:

Richard D. Lieberman’s FAR Consulting & Training at https://www.richarddlieberman.com/, and Mistakes in Government Contracting at https://richarddlieberman.wixsite.com/mistakes.


10 views0 comments

Recent Posts

See All

The website of Richard Donald Lieberman, a government contracts consultant and retired attorney who is the author of both "The 100 Worst Mistakes in Government Contracting" (with Jason Morgan) and "The 100 Worst Government Mistakes in Government Contracting." Richard Lieberman concentrates on Federal Acquisition Regulation (FAR) consulting and training, including  commercial item contracting (FAR Part 12), compliance with proposal requirements (FAR Part 15 negotiated procurement), sealed bidding (FAR Part 14), compliance with solicitation requirements, contract administration (FAR Part 42), contract modifications and changes (FAR Part 43), subcontracting and flowdown requirements (FAR Part 44), government property (FAR Part 45), quality assurance (FAR Part 46), obtaining invoiced payments owed to contractors,  and other compliance with the FAR. Mr.Lieberman is also involved in numerous community service activities.  See LinkedIn profile at https://www.linkedin.com/in/richard-d-lieberman-3a25257a/.This website and blog are for educational and information purposes only.  Nothing posted on this website constitutes legal advice, which can only be obtained from a qualified attorney. Website Owner/Consultant does not engage in the practice of law and will not provide legal advice or legal services based on competence and standing in the law. Legal filings and other aspects of a legal practice must be performed by an appropriate attorney. Using this website does not establish an attorney-client relationship. Although the author strives to present accurate information, the information provided on this site is not guaranteed to be complete, correct or up-to-date.  The views expressed on this blog are solely those of the author. FAR Consulting & Training, Bethesda, Maryland, Tel. 202-520-5780, rliebermanconsultant@gmail.com

Copyright © 2024 Richard D. Lieberman

bottom of page