Market Shortage Not An Excuse for Nonperformance-Default Justified

In a recent Army commercial contract for leasing and maintenance of trucks, the Armed Services Board of Contract Appeals held there was a prima facie showing of default, and found no merit in any of the excuses for failure to deliver the required trucks.  SBA Contracting, LLC, ASBCA No. 63320, October 3, 2023.

 

The Army awarded a commercial items contract to Sama Bna Aliraq Company (“SBA”) which required SBA to lease and maintain several types of trucks.  The contract included FAR 52.212-4, Contract Terms and Conditions-Commercial Products and Commercial Services.  The delivery date for all 12 of the trucks in the contract was May 1, 2022.  When SBA failed to deliver all but one truck by the delivery date, the Army had the right to terminate the contract for cause, which it did. 

 

The only remaining significant issue was whether the failure to deliver the trucks was excusable.  On this point the Board held the following:

 

·       The contract required a single delivery date, and various trucks in the contract were not severable

·       Although SBA asserted that the delivery date had been extended to July 1, 2022, the Board could find no formal or informal agreement to so extend the date.

·       SBA alleged that the default should be excused because SBA had insufficient time to deliver the trucks in light of a vehicle shortage in Iraq which was beyond its control. The Board rejected that excuse, nothing that “market shortage is not an excusable cause for nonperformance” and SBA could not demonstrate that it was impossible to obtain the trucks

·       The Board rejected SBA’s excuse for the COVID-19 pandemic as a cause of its default.  The Board could find no contract language that shifted the risk in this firm fixed price contract from the contractor to the Government for COVID-19.

·       The Board rejected the SBA’s “prior course of dealing” argument, where SBA alleged that the government had relaxed requirements for other contractors.  The Board noted that “[j]ustifiable reliance on a prior course of dealing requires proof of the same contracting agency, the same contractor and essentially the same contract provisions.”  SBA was not a party to the prior contracts that it cited.

·       The Board rejected SBA’s view that the termination decision was arbitrary, capricious or an abuse of discretion.  The Board noted the contracting officer’s broad discretion in terminating for cause, and applied a four factors test:

1.     Whether the government official acted with subjective bad faith

2.     Whether the official had a reasonable contract-related basis supporting the decision

3.     The amount of discretion vested in the official whose action is being reviewed and

4.     Whether a proven violation of relevant statutes or regulations can render the decision arbitrary and capricious

 

The Board rejected this argument and found no evidence of bad faith, that the CO had a reasonable contract-related basis to terminate for cause, and the CO had broad discretion.

 

The Board held that SBA failed to demonstrate that the default was excusable or that the termination was arbitrary, capricious or an abuse of the CO’s discretion.

 

Takeaway.  Any challenge to a termination for cause (default) requires clear cut evidence of reasons that grant the contractor the right to have its default excused.  Similarly, the bad faith argument also requires valid proof.

 

 

For other helpful suggestions on government contracting, visit:

Richard D. Lieberman’s FAR Consulting & Training at https://www.richarddlieberman.com/, and Mistakes in Government Contracting at https://richarddlieberman.wixsite.com/mistakes.

5 views0 comments

Recent Posts

See All

Asserting Duress in Signing a Modification

Sand Point Services, LLC brought two claims before the Armed Services Board of Contract Appeals, both involving modifications.  Sand Point Servs., LLC, ASBCA Nos. 61819, 61820, January 4, 2024.  The f

Requirements Contracts: Words of Exclusivity

The Federal Circuit recently clarified that an agency’s contract may still contain requisite language to make it a requirements contract, even if the contract does not include the required Federal Acq

The website of Richard Donald Lieberman, a government contracts consultant and retired attorney who is the author of both "The 100 Worst Mistakes in Government Contracting" (with Jason Morgan) and "The 100 Worst Government Mistakes in Government Contracting." Richard Lieberman concentrates on Federal Acquisition Regulation (FAR) consulting and training, including  commercial item contracting (FAR Part 12), compliance with proposal requirements (FAR Part 15 negotiated procurement), sealed bidding (FAR Part 14), compliance with solicitation requirements, contract administration (FAR Part 42), contract modifications and changes (FAR Part 43), subcontracting and flowdown requirements (FAR Part 44), government property (FAR Part 45), quality assurance (FAR Part 46), obtaining invoiced payments owed to contractors,  and other compliance with the FAR. Mr.Lieberman is also involved in numerous community service activities.  See LinkedIn profile at https://www.linkedin.com/in/richard-d-lieberman-3a25257a/.This website and blog are for educational and information purposes only.  Nothing posted on this website constitutes legal advice, which can only be obtained from a qualified attorney. Website Owner/Consultant does not engage in the practice of law and will not provide legal advice or legal services based on competence and standing in the law. Legal filings and other aspects of a legal practice must be performed by an appropriate attorney. Using this website does not establish an attorney-client relationship. Although the author strives to present accurate information, the information provided on this site is not guaranteed to be complete, correct or up-to-date.  The views expressed on this blog are solely those of the author. FAR Consulting & Training, Bethesda, Maryland, Tel. 202-520-5780, rliebermanconsultant@gmail.com

Copyright © 2024 Richard D. Lieberman

bottom of page