top of page
  • Writer's pictureR.D. Lieberman,Consultant

Contracting Officer Must Consider Request for Equitable Adjustment In Good Faith and Reasonableness

The Federal Circuit recently considered the Federal Acquisition Regulation (“FAR”) language which requires a Contracting Officer to “consider an equitable adjustment to the contract” if required government furnished property in a contract is not delivered to the contractor. FAR 52.245-1(d)(2). See BGT Holdings, LLC v. United States, No. 2020-1084 (Fed. Cir. Dec. 23, 2020). Rejecting the Government’s and the Court of Federal Claims interpretation that the only obligation of the government is to “think over” a contractor’s request for equitable adjustment (“REA”), the Federal Circuit makes it clear that such consideration holds the government to a duty of good faith and reasonableness.


BGT contracted with the Navy to construct and deliver a gas Turbine generator. The Navy agreed to supply certain government furnished equipment (“GFE”) that BGT would use to construct the generator. Two important items of GFE were an exhaust collector and engine mounts, items which the Navy ultimately never delivered to BGT.


The contract included the standard GFE clause, FAR 52.245-1, which requires the government to deliver GFE as described in the contract, and states that “[i]f the property is not delivered to the Contractor by the dates stated in the contract, the Contracting Officer, shall, upon the Contractor’s timely written request, consider an equitable adjustment to the contract.” The clause also gives the government the right to increase or decrease GFE under the contract, but if it does so, the Contracting Officer is required to “consider an equitable adjustment.”


The Navy informed BFT that the Navy would not deliver the exhaust collector and engine mounts unless BGT provided a “cost savings” to the Navy—a decrease in contract price. BGT declined to offer a cost savings for the items that were to be provided as GFE, and the Navy then reallocated these items as fleet assets, and notified BGT that they were no longer available. To continue performing under the contract BGT purchased those items on the commercial market for $610,775. BGT then requested an equitable adjustment for that cost. When the Navy received the completed gas turbine generator it accepted it, but rejected BFT’s request for an equitable adjustment for the exhaust collector and engine mounts.


BGT’s appeal in the court was that the Navy breached the government property clause, FAR 52.245-1, by failing to provide an equitable adjustment after the Navy withheld the GFE items it had agreed to deliver under the contract. Although there are other aspects of the case, this was the most important one.


The Navy’s defense was that FAR 52.245-1(d)(2)(i) merely requires a contracting officer to “consider BGT’s request for an equitable adjustment—not to grant the adjustment to BGT.” The Court rejected the government’s interpretation of the term “shall consider” because it would produce “absurd results” under the government property clause. It is implausible to believe that the Navy’s only obligation would be to merely “think over” BFT’s request, before denying it. The Court held that the correct interpretation of “shall consider” in this contract setting doesn’t give the government absolute discretion, but holds the government to a duty of good faith and reasonableness. Contracting officers must exercise their discretion in good faith, and perform that duty reasonably. The Court vacated the dismissal of BFT’s claim, and remanded the case to the Court of Federal Claims.


Takeaway: When the FAR speaks of the contracting officer “considering an equitable adjustment” (such as in the Government Furnished Property clause or the Changes Clause), this does not mean just "think it over." The Government must consider such an REA in good faith and grant relief that is appropriate to the contractor and consistent with the contract.


For other helpful suggestions on government contracting, visit:

Richard D. Lieberman’s FAR Consulting & Training at https://www.richarddlieberman.com/, and Mistakes in Government Contracting at https://richarddlieberman.wixsite.com/mistakes.

27 views0 comments

Recent Posts

See All

Asserting Duress in Signing a Modification

Sand Point Services, LLC brought two claims before the Armed Services Board of Contract Appeals, both involving modifications.  Sand Point Servs., LLC, ASBCA Nos. 61819, 61820, January 4, 2024.  The f

Requirements Contracts: Words of Exclusivity

The Federal Circuit recently clarified that an agency’s contract may still contain requisite language to make it a requirements contract, even if the contract does not include the required Federal Acq

The website of Richard Donald Lieberman, a government contracts consultant and retired attorney who is the author of both "The 100 Worst Mistakes in Government Contracting" (with Jason Morgan) and "The 100 Worst Government Mistakes in Government Contracting." Richard Lieberman concentrates on Federal Acquisition Regulation (FAR) consulting and training, including  commercial item contracting (FAR Part 12), compliance with proposal requirements (FAR Part 15 negotiated procurement), sealed bidding (FAR Part 14), compliance with solicitation requirements, contract administration (FAR Part 42), contract modifications and changes (FAR Part 43), subcontracting and flowdown requirements (FAR Part 44), government property (FAR Part 45), quality assurance (FAR Part 46), obtaining invoiced payments owed to contractors,  and other compliance with the FAR. Mr.Lieberman is also involved in numerous community service activities.  See LinkedIn profile at https://www.linkedin.com/in/richard-d-lieberman-3a25257a/.This website and blog are for educational and information purposes only.  Nothing posted on this website constitutes legal advice, which can only be obtained from a qualified attorney. Website Owner/Consultant does not engage in the practice of law and will not provide legal advice or legal services based on competence and standing in the law. Legal filings and other aspects of a legal practice must be performed by an appropriate attorney. Using this website does not establish an attorney-client relationship. Although the author strives to present accurate information, the information provided on this site is not guaranteed to be complete, correct or up-to-date.  The views expressed on this blog are solely those of the author. FAR Consulting & Training, Bethesda, Maryland, Tel. 202-520-5780, rliebermanconsultant@gmail.com

Copyright © 2024 Richard D. Lieberman

bottom of page