Claims Court Lacks Jurisdiction over Task Order Size Protests, Including Bid Protests

The Federal Circuit recently affirmed the decision of the Court of Federal Claims that it had no jurisdiction over a bid protest challenge of a size determination made by the Small Business Administration (“SBA”) Office of Hearings and Appeals (“OHA”), in connection with the issuance of a task order. 22nd Century Tech., Inc. v United States, No. 2022-1275 (Fed. Cir. Jan. 10, 2023). The Federal Acquisition Streamlining Act of 1994 (“FASA”) specifically bars the Claims Court from exercising jurisdiction over 22nd Century’s bid protest.


The case relates to a task order issued under an Army Indefinite Delivery, Indefinite Quantity (“IDIQ”) multiple award contract that involved proposals for Command, Control Computers, Intelligence and Surveillance needs. The solicitation was not set-aside for small business but allowed the Army to restrict subsequent task order competitions to small business contractors. In 2015, when 22nd Century submitted its proposal for the IDIQ contract, it was a small business. However, in December 2020, the Army issued a Task Order Request for Proposals under this IDIQ contract which limited competition to small businesses and required proposals to represent whether the submitter was small or not for purposes of the Task Order. Although 22nd Century was no longer small, it represented that it had been “a small business for this IDIQ” (at the time of its proposal in 2015).


In two formal size determinations, OHA held that 22nd Century was other-than small for purposes of the Task Order RFP. 22nd Century brought a bid protest under the Tucker Act, requesting that the Claims Court set aside OHA’s determination. The company argued that because the Request for Proposals under the Task Order did not contain an explicit request for recertification, SBA must measure must measure 22nd Century’s size on the date it submitted its proposal for the IDIQ contract.


The government moved to dismiss the complaint, arguing that FASA, in10 U.S.C. § 3406 (f)(1) (see below) barred review of the bid protest because the challenged actions by the SBA and the Army were “in connection with the issuance or proposed issuance of a task or delivery order.” This section is as follows:


(f) Protests. - (1) A protest is not authorized in connection with the issuance or proposed issuance of a task or delivery order except for-

(A) a protest on the ground that the order increases the scope, period, or maximum value of the contract under which the order is issued; or

(B) a protest of an order valued in excess of $25,000,000.

(2) Notwithstanding section 3556 of title 31, the Comptroller General of the United States shall have exclusive jurisdiction of a protest authorized under paragraph (1)(B).


10 U.S.C. § 3406(f)


The Federal Circuit noted that in FASA, the jurisdiction of the Claims court was limited in the context of protests of task or delivery orders, whether in the sense of a bid protest (such as an award protest) or a challenge to a size determination, where the size determination is issued in connection of a task or delivery order. The Federal Circuit affirmed that the Claims Court had correctly concluded that it lacked jurisdiction over this protest.


Takeaway. Challenges of bid protests in connection with a task or delivery order (except those alleging that the order increases the scope, period of maximum value of the contract, or a protest of an order valued in excess of $25 million) cannot be taken to the Claims Court, but can be submitted to the Comptroller General (the Governmental Accountability Office, GAO).


For other helpful suggestions on government contracting, visit:

Richard D. Lieberman’s FAR Consulting & Training at https://www.richarddlieberman.com/, and Mistakes in Government Contracting at https://richarddlieberman.wixsite.com/mistakes.


10 views0 comments

Recent Posts

See All

Asserting Duress in Signing a Modification

Sand Point Services, LLC brought two claims before the Armed Services Board of Contract Appeals, both involving modifications.  Sand Point Servs., LLC, ASBCA Nos. 61819, 61820, January 4, 2024.  The f

Requirements Contracts: Words of Exclusivity

The Federal Circuit recently clarified that an agency’s contract may still contain requisite language to make it a requirements contract, even if the contract does not include the required Federal Acq

The website of Richard Donald Lieberman, a government contracts consultant and retired attorney who is the author of both "The 100 Worst Mistakes in Government Contracting" (with Jason Morgan) and "The 100 Worst Government Mistakes in Government Contracting." Richard Lieberman concentrates on Federal Acquisition Regulation (FAR) consulting and training, including  commercial item contracting (FAR Part 12), compliance with proposal requirements (FAR Part 15 negotiated procurement), sealed bidding (FAR Part 14), compliance with solicitation requirements, contract administration (FAR Part 42), contract modifications and changes (FAR Part 43), subcontracting and flowdown requirements (FAR Part 44), government property (FAR Part 45), quality assurance (FAR Part 46), obtaining invoiced payments owed to contractors,  and other compliance with the FAR. Mr.Lieberman is also involved in numerous community service activities.  See LinkedIn profile at https://www.linkedin.com/in/richard-d-lieberman-3a25257a/.This website and blog are for educational and information purposes only.  Nothing posted on this website constitutes legal advice, which can only be obtained from a qualified attorney. Website Owner/Consultant does not engage in the practice of law and will not provide legal advice or legal services based on competence and standing in the law. Legal filings and other aspects of a legal practice must be performed by an appropriate attorney. Using this website does not establish an attorney-client relationship. Although the author strives to present accurate information, the information provided on this site is not guaranteed to be complete, correct or up-to-date.  The views expressed on this blog are solely those of the author. FAR Consulting & Training, Bethesda, Maryland, Tel. 202-520-5780, rliebermanconsultant@gmail.com

Copyright © 2024 Richard D. Lieberman

bottom of page